• Status Closed
  • Percent Complete
    100%
  • Task Type Maintenance
  • Category Datacenter → Jena1
Attached to Section: Network
Opened by Admin - 2016-08-02

FS#1892 - Planned Maintenance CLT (Jena/Amsterdam) 20./21.08.2016

Details der Wartungsarbeit /Planned Works Details:

Start Datum & Zeit / Start Date & Time: 20/08/2016 23:00 (GMT)* (01:00 CEST)
End Datum & Zeit / End Date & Time: 21/08/2016 05:00 (GMT)* (07:00 CEST)

Ausfalldauer / Outage Duration: bis zu/ for up to 240 Minutes
Closed by Admin
Monday, 22 August 2016, 06:58 GMT
Reason for closing:  Finished
Admin
Sunday, 21 August 2016, 06:22 GMT
Maintenance finished.
Downtime of connection was about 30mins.
No impact for customers detected.
Admin
Sunday, 21 August 2016, 16:31 GMT
additional work required:
---
Details der Wartungsarbeit /Planned Works Details:

Start Datum & Zeit / Start Date & Time: 21/08/2016 22:00 (GMT)*
End Datum & Zeit / End Date & Time: 22/08/2016 02:00 (GMT)*

Legend

Task Type

The type of the task. normal work for all services

Category

The category of the task. normal work for all services with upcoming tasks / announcements

Summary

A short summary of the task. active issues or failures

Status

The status of the task. service status unknown or not updated yet

Last Edited

The date when the task was last edited.

Progress

The progress of the task in percent.