- Category Datacenter → Jena1
FS#2039 - Planned Maintenance CLT Jena => Amsterdam
Wartungsarbeits (WA) -Ref./ Planned Work (PW) Ref.: CRQ1-2383708850
Start Datum & Zeit / Start Date & Time: 17/02/2017 23:00 (GMT) (18/02/2017 00:00 (CET))
End Datum & Zeit / End Date & Time: 18/02/2017 04:00 (GMT) (18/02/2017 05:00 (CET))
Ausfalldauer / Outage Duration: bis zu/ for up to 180 Minutes
Start Datum & Zeit / Start Date & Time: 17/02/2017 23:00 (GMT) (18/02/2017 00:00 (CET))
End Datum & Zeit / End Date & Time: 18/02/2017 04:00 (GMT) (18/02/2017 05:00 (CET))
Ausfalldauer / Outage Duration: bis zu/ for up to 180 Minutes
Closed by Admin
Saturday, 18 February 2017, 12:12 GMT
Reason for closing: Finished
Saturday, 18 February 2017, 12:12 GMT
Reason for closing: Finished