• Status Closed
  • Percent Complete
    100%
  • Task Type Change
  • Category All Services → Dedicated Servers
Attached to Section: Datacenter
Opened by Admin - 2018-09-25

FS#2339 - relocation DCJ1-C row C

relocation DCJ1-C row C
Closed by Admin
Wednesday, 10 October 2018, 15:17 GMT
Reason for closing:  Finished
Admin
Tuesday, 02 October 2018, 13:19 GMT
planned date for relocation rack c-c-04/c-c-05/c-c-06: 02.10.2018
Downtime up to 360 Minutes
Admin
Wednesday, 03 October 2018, 05:51 GMT
Work for today was done
Admin
Friday, 05 October 2018, 07:26 GMT
planned date for relocation rack c-c-02/c-c-03/c-c-04: 02.10.2018
Downtime up to 360 Minutes
Admin
Wednesday, 10 October 2018, 07:51 GMT
planned date for relocation rack c-c-01/c-c-02: 10.10.2018
Downtime up to 360 Minutes
Admin
Wednesday, 10 October 2018, 15:17 GMT
Work was done for today. All customer servers relocated to MOD-A

Legend

Task Type

The type of the task. normal work for all services

Category

The category of the task. normal work for all services with upcoming tasks / announcements

Summary

A short summary of the task. active issues or failures

Status

The status of the task. service status unknown or not updated yet

Last Edited

The date when the task was last edited.

Progress

The progress of the task in percent.