113 | Maintenance | Fra1 | Planned Maintenance AMSIX 2015-10-07 00:00 - ... | Closed | 2015-10-07 |
|
112 | Maintenance | Fra1 | Planned Maintenance SWISSIX 2015-09-23 00:00 ... | Closed | 2015-09-23 |
|
110 | Maintenance | Fra1 | Planned Maintenance BCIX 2015-09-18 00:00 - 0... | Closed | 2015-09-18 |
|
114 | Maintenance | Fra1 | Planned Maintenance NTT Transit in Frankfurt ... | Closed | 2015-09-14 |
|
104 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 02.09.2015 - 04.09.... | Closed | 2015-09-04 |
|
102 | Maintenance | Ef1 | Planned Maintenance TNK 3+4 2015-09-01 05:00... | Closed | 2015-09-01 |
|
100 | Maintenance | Fra1 | Planned Maintenance VIX 2015-08-16 00:00 - 06... | Closed | 2015-08-16 |
|
98 | Maintenance | Fra1 | Planned Maintenance Cogent Transit Frankfurt ... | Closed | 2015-07-28 |
|
91 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 24.06.2015 (00:00 -... | Closed | 2015-06-24 |
|
86 | Maintenance | Jena1 | Planned Maintenance BCIX-Peering 2015-06-21 | Closed | 2015-06-22 |
|
87 | Maintenance | Jena1 | Planned Maintenance VIX-Peering 2015-06-12 | Closed | 2015-06-17 |
|
93 | Maintenance | Jena1 | Planned Maintenance AMSIX 2015-06-14 00:00 - ... | Closed | 2015-06-15 |
|
83 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 11.06.2015 (00:00 -... | Closed | 2015-06-11 |
|
82 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 03.06.2015 (00:00 -... | Closed | 2015-06-03 |
|
88 | Maintenance | All Services | Maintenance AMS 2015-05-31 | Closed | 2015-05-31 |
|
81 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 29.5.2015 (00:00 -... | Closed | 2015-05-29 |
|
70 | Maintenance | Fra1 | Planned Work FRA-Jena 10G 12.5.2015 | Closed | 2015-05-28 |
|
80 | Maintenance | Fra1 | Planned Maintenance COGENT-Transit in Frankfu... | Closed | 2015-05-20 |
|
76 | Maintenance | Jena1 | Planned Work FRA-Jena 10G 28.5.2015 (00:00 -... | Closed | 2015-05-13 |
|
78 | Maintenance | Fra1 | Planned Maintenance NTT Transit in Frankfurt ... | Closed | 2015-05-11 |
|
77 | Maintenance | Jena1 | Planned Work ERF-Jena 07.05.2015-08.05.2015 -... | Closed | 2015-05-08 |
|
75 | Maintenance | All Services | Maintenance BCIX 5.5.2015 23:00 - 6.5.2015 07... | Closed | 2015-05-06 |
|
74 | Maintenance | All Services | Maintenance FRA<->ERF Colt 5.5.2015 22:00 - 6... | Closed | 2015-05-06 |
|
73 | Maintenance | Datacenter | Maintenance FRA <-> VIX, 02.05.2015 | Closed | 2015-05-03 |
|
71 | Maintenance | All Services | Maintance VIX | Closed | 2015-05-01 |
|
63 | Maintenance | All Services | Maintance Frankfurt / NTT Transit | Closed | 2015-04-17 |
|
57 | Maintenance | Jena1 | Maintenance FRA <-> ERF / 21.03.2015 | Closed | 2015-03-23 |
|
55 | Maintenance | All Services | Maintance FRA-AMS (Amsix) from 10.3.2015 23:0... | Closed | 2015-03-16 |
|
46 | Maintenance | Datacenter | Maintenance SWISS-IX + V-IX / 15.11.2014 | Closed | 2014-11-19 |
|
41 | Maintenance | All Services | Maintenance 06.11 | FRA <--> BCIX | Closed | 2014-11-06 |
|
34 | Maintenance | All Services | Maintenance Colt from 11.10.2014 00:00 to 11.... | Closed | 2014-10-11 |
|
6 | Maintenance | Fra1 | Maintenance DECIX from 05.02.2014 04:00 to 05... | Closed | 2014-02-05 |
|
186 | Modernization | Involved Service | VLAN gateway outage | In progress | 2017-01-01 |
|
169 | Modernization | All Services | Reworking WAN backbone / BGP4 | In progress | 2016-11-29 |
|
3 | Modernization | Involved Service | resolver at fdns3+4 does not work properly | Closed | 2014-11-06 |
|
140 | Securing | Datacenter | DHCP server issue / securing DC network | In progress | 2018-12-04 |
|
196 | Termination | Involved Service | Termination AMSIX peering port | Closed | 2023-02-11 |
|
177 | Termination | Involved Service | remove BCIX peering connection | Closed | 2019-02-07 |
|
156 | Termination | Involved Service | remove SwissIX peering connection | Closed | 2018-11-17 |
|
172 | Termination | Fra1 | remove VIX peering connection | Closed | 2018-11-17 |
|
194 | Termination | Involved Service | remove DECIX peering connection | Closed | 2017-09-25 |
|
171 | Termination | All Services | shutdown old WAN backbone | In progress | 2017-06-14 |
|
33 | Termination | All Services | remove connections to EF / remove POP EF | Closed | 2016-07-07 |
|
2 | Termination | Fra1 | Termination TATA-Transit | Closed | 2014-03-03 |
|
261 | Upgrade | Involved Service | upgrade datacenter router dsw-c6kb | Waiting | 2021-04-20 |
|
277 | Upgrade | All Services | Upgrade HLkomm Transit | Closed | 2019-11-01 |
|
195 | Upgrade | Involved Service | Upgrade Kleyrex peering port | Closed | 2019-05-01 |
|
216 | Upgrade | Fra1 | upgrade backbone router bbsw-h4a-fra | Closed | 2019-01-16 |
|
258 | Upgrade | All Services | upgrade WDM equipment POP TNK | Closed | 2019-01-04 |
|
260 | Upgrade | Involved Service | upgrade datacenter router dsw-c6ka | Closed | 2018-10-26 |
|